Close Menu
  • Home
  • AI
  • Education
  • Entertainment
  • Food Health
  • Health
  • Sports
  • Tech
  • Well Being

Subscribe to Updates

Subscribe to our newsletter and never miss our latest news

Subscribe my Newsletter for New Posts & tips Let's stay updated!

What's Hot

DoorDash CEO Tony Xu Loves 2,000-Word Emails From Customers, Dashers

March 30, 2026

Delaware Judge Reassigns Elon Musk Cases After LinkedIn Emoji Spat

March 30, 2026

Mantis Biotech is making ‘digital twins’ of humans to help solve medicine’s data availability problem

March 30, 2026
Facebook X (Twitter) Instagram
  • Home
  • About Us
  • Advertise With Us
  • Contact us
  • DMCA
  • Privacy Policy
  • Terms & Conditions
Facebook X (Twitter) Instagram
IQ Times Media – Smart News for a Smarter YouIQ Times Media – Smart News for a Smarter You
  • Home
  • AI
  • Education
  • Entertainment
  • Food Health
  • Health
  • Sports
  • Tech
  • Well Being
IQ Times Media – Smart News for a Smarter YouIQ Times Media – Smart News for a Smarter You
Home » xAI is facing a lawsuit for operating over 400 MW of gas turbines without permits
AI

xAI is facing a lawsuit for operating over 400 MW of gas turbines without permits

IQ TIMES MEDIABy IQ TIMES MEDIAJune 18, 2025No Comments3 Mins Read
Facebook Twitter Pinterest LinkedIn Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email


The Colossus data center operated by xAI outside of Memphis is facing a lawsuit for operating a fleet of natural gas turbines without permits.

“Over the past year, xAI has installed and operated at least 35 combustion turbines and other sources of air pollution at the Colossus site without ever obtaining the necessary preconstruction or operating air permits,” the Southern Environmental Law Center (SELC) wrote in a letter to xAI.

The legal group submitted the letter on behalf of the NAACP. It serves as a notice for intent to sue xAI for violations of the Clean Air Act. The law requires organizations to submit such a letter 60 days in advance of filing a lawsuit. 

The gas turbines have the potential to emit more than 2,000 tons of NOx per year, a group of chemicals that contribute to smog. 

Memphis already “had some of the worst air quality in the region,” SELC notes. “In 2024, Memphis was deemed an asthma capital of the nation by the Asthma and Allergy Foundation of America due to high rates of emergency room visits and deaths from asthma.”

SELC alleges that xAI failed to obtain permits required by both the federal and local regulators before installing the generators. It also alleges that the company wasn’t operating them with proper air pollution controls. At one point, xAI had enough turbines to generate 421 megawatts of electricity.

Last summer, the Shelby County Health Department (SCHD), which oversees local air pollution compliance, “told reporters that xAI’s turbines were exempt from permitting, although SCHD still had not disclosed publicly what xAI was operating on its site nor the legal basis for any such exemption,” SELC said.

To determine what was happening at the Colossus site, SELC paid an aerial photographer to capture images of the facility in March. The photos revealed that xAI had installed 35 turbines around the perimeter of the data center at the time. Thermal images taken about a month later showed that at least 33 of them were operational, SELC said.

After those images were taken, the Greater Memphis Chamber, a local economic development agency, said that xAI had removed some of the turbines.

“The temporary natural gas turbines that were being used to power the Phase I GPUs prior to grid connection are now being demobilized and will be removed from the site over the next two months,” the Memphis Chamber said. “About half of the operating turbines will remain” until a second substation completes the data center’s connection to the grid, the organization added, and that once the substation was complete, the turbines would serve as backups.

But a flight on June 15 showed that at least 26 turbines remained, including three new ones that had been installed since the April flight. The total generating capacity was around 407 megawatts, just 14 megawatts shy of the previous amount.

“With very few exceptions — none of which apply here — new sources of criteria and other air pollutants in Tennessee must obtain preconstruction approval in the form of an air permit as well as a permit to operate and emit pollutants,” SELC said. 



Source link

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
IQ TIMES MEDIA
  • Website

Related Posts

Mantis Biotech is making ‘digital twins’ of humans to help solve medicine’s data availability problem

March 30, 2026

ScaleOps raises $130M to improve computing efficiency amid AI demand

March 30, 2026

AI chip startup Rebellions raises $400 million at $2.3B valuation in pre-IPO round

March 30, 2026
Add A Comment
Leave A Reply Cancel Reply

Editors Picks

Justice Department targets Minnesota in transgender athletes lawsuit

March 30, 2026

2 students dead and 7 injured in Tennessee school bus crash

March 27, 2026

Suburban Detroit school settles lawsuit over Pledge of Allegiance

March 27, 2026

Changes to Native American tuition waiver could expand access to higher education for thousands

March 27, 2026
Education

Justice Department targets Minnesota in transgender athletes lawsuit

By IQ TIMES MEDIAMarch 30, 20260

MINNEAPOLIS (AP) — The Trump administration sued Minnesota and its school athletics governing body on…

2 students dead and 7 injured in Tennessee school bus crash

March 27, 2026

Suburban Detroit school settles lawsuit over Pledge of Allegiance

March 27, 2026

Changes to Native American tuition waiver could expand access to higher education for thousands

March 27, 2026
IQ Times Media – Smart News for a Smarter You
Facebook X (Twitter) Instagram Pinterest Vimeo YouTube
  • Home
  • About Us
  • Advertise With Us
  • Contact us
  • DMCA
  • Privacy Policy
  • Terms & Conditions
© 2026 iqtimes. Designed by iqtimes.

Type above and press Enter to search. Press Esc to cancel.